Flagship project
Muchenje Solar PV Plant, 20 MWp with storage.
Chieftainess Mungule area, Chibombo District, Central Province. Forty one hectares of titled land, nine kilometres from a new ZESCO substation.
The site
Chosen for the connection, not just the sunshine.
Most solar sites in Zambia have good irradiance. Far fewer have flat ground, clean title and a substation within a short line route. Muchenje has all three, which is why it can reach financial close on a realistic timetable.
The parcel is held under a 99-year leasehold title owned by the sponsors, so there is no land assembly risk and no dispute to resolve before construction. The flat topography keeps earthworks and drainage costs down and makes the 33 kV evacuation line simple to build.
The solar resource
Where Chibombo sits on the national irradiation map.
Central Province receives a daily average in the 5.5 to 6.0 kWh per square metre band. The map below is the World Bank Global Solar Atlas layer for Zambia, measured over 1994 to 2017.
Technical summary
What gets built.
Money and offtake
USD 31 million, and a tariff that has to stand up.
The capital estimate covers modules, inverters, balance of plant, the battery system and the 33 kV line, benchmarked against similar projects in southern Africa rather than a global average.
On the revenue side, storage is what makes the number work. Firm evening capacity is worth more to the system than midday energy, and it is what lets a tariff survive scrutiny from the regulator and from lenders.
Where the project stands
Development sequence.
Land and company in place
Company incorporated, 41 hectares held under title, site identified against the new substation. Complete.
Feasibility and technical design
Resource assessment, plant layout, storage sizing and the interconnection route. In progress.
Equity partner and permits
Partner selection alongside the generation licence application, environmental and social approval and land conversion. Open now.
Offtake and financial close
Power purchase agreement with ZESCO, tariff approval, debt package and EPC award.
Construction and commissioning
Build the array, the battery system and the evacuation line, then commission into the grid and begin the 25-year operating period.
Alignment
Why the project fits national and global policy.
Affordable and clean energy
Adds non-hydro renewable capacity to a system that depends on rainfall for most of its generation.
Climate action
Displaces emergency thermal generation and imported power during dry years.
Work and growth
Construction employment, trade training and a permanent operations team in Chibombo District.
National Energy Policy 2019
Directly supports the policy's private generation and diversification objectives and the 8NDP investment targets.
The project file is ready to share.
Feasibility work, land title, interconnection study and draft offtake terms, released under a mutual confidentiality agreement.